2013 Construction Map
5-Year Paving Plan
5-Year Sewer & Water Plan
2013 - 2017 Capital Improvement Plan street listing
Plans and specifications will be available on the City of Appleton’s website at www.appleton.org. Go to: Department…, Public Works…, Admin/Engineering…, Projects Open for Bid. Plans and specifications may also be picked up in the office of the City Engineer, City Center, Fifth floor, 100 N. Appleton Street, Appleton, Wisconsin 54911 There is no cost to download the Plans and Specifications from the website. Plans and specifications picked up at the office of the City Engineer will cost $50.00 for each set. No cash please. No refunds will be issued. Plans and specifications will not be mailed.
BB-08 Riverheath Sewer and Water
Project Engineer, Keith Curran, 832-6462, keith.curran@appleton.org
Anticipated plan/spec availability is 7/8/13
Anticipated bid opening is 7/22/13
N-13 Sewer Spot Repair
Project Engineer, Chad Weyenberg, 832-5915, chad.weyenberg@appleton.org
Anticipated plan/spec availability is 7/15/13
Anticipated bid opening is 7/29/13
J-13 Mini Storm Sewer construction
Project Engineer, Keith Curran, 832-6462, Keith.curran@appleton.org
Anticipated plan/spec availability is 7/15/13
Anticipated bid opening is 7/29/13
Y-13 Waste Water Treatment Plant Storm Sewer Tunneling Project
Project Engineer, Keith Curran, 832-6462, keith.curran@appleton.org
Anticipated plan/spec availability is 8/26/13
Anticipated bid opening is 9/9/13
U-13 Cherryvale Avenue Sewer and Water , and Grade and Gravel
Project Engineer, Randey Felton, 832-6483, randey.felton@appleton.org
Anticipated plan/spec availability is 8/5/13
Anticipated bid opening is 8/19/13
|
 |
 |
|
 |